Solar Developer Documents

How to Apply for Interconnection at Four County EMC

If you are installing a certified, inverter-based solar or DER system less than 20 kW AC, please follow the steps below to apply for interconnection. For DER systems greater than 20 kW AC, please see the Commercial or Utility-Scale Developers section at the bottom on the page.

Step 1: Complete the Interconnection Request Form by clicking the link below.

Download and complete the latest version of the 20kW Inverter-Based Interconnection Request Form

Upload all documents to the form link: Solar Interconnection Application

Be sure to fill out all required sections. Incomplete forms will delay processing.

Step 2: Submit Your Application

Upload the completed form and required documents using the upload link provided above.

Once received, our team will review the application and notify you of the next steps.

Step 3: Watch for Status Updates

You will receive email updates as your application progresses through key stages:

  • In Review

  • Approved for Construction

  • Permission to Operate (PTO)

As the application progresses, you will be emailed instructions on next steps, as well as a link to upload follow up forms. Please use that emailed link to upload any follow-up documentation requested by our team.

Need Help or a Walkthrough?

We’re here to help! If you have questions or would like to schedule a virtual demo of the process:
Email us at solarapplication@fourcty.org

 

Residential Developers

20kW Inverter-Based Interconnection Request Form

Small Renewable Rider

 

Commercial or Utility-Scale Developers

Application Agreement

Interconnection Agreement

Commercial Renewable Rider